Supply chain woes further delay launch of SDA’s first operational satellites

The Space Development Agency has once again pushed back the launch of its first batch of operational data transport and missile-tracking satellites, and is now targeting a date in “late summer 2025” to put the space vehicles on orbit.
SDA announced the delay for Tranche 1 of the Proliferated Warfighter Space Architecture (PWSA) in a statement on Friday, citing continued supply chain woes as the main contributor to the decision to postpone launch. The agency plans to conduct around one launch per month until all 154 Tranche 1 sats are on orbit.
The news marks yet another setback for SDA, which in recent weeks has been grappling with leadership changes and questions regarding the agency’s semi-independent acquisition authorities. However, the launch delay appears to be caused by supply chain bottlenecks related to the sheer number of satellites the agency plans to put on orbit.
“SDA continues to aggressively work toward the first Tranche 1 launch; however, as we progress through a normal assembly, integration, and testing campaign, with the added challenge of late supplier deliveries, it has become clear additional time is required for system readiness to meet the Tranche 1 minimum viable capability,” the agency said in a statement.
The PWSA is a planned constellation comprising hundreds of satellites stationed in low-Earth orbit. The program is divided into two main mission areas — data relay and communications in the transport layer, and missile warning and tracking in the tracking layer. SDA initially pursued an aggressive acquisition and launch schedule known as “spiral development,” which sought to put new satellites in space every two years.
The agency originally planned to begin launching Tranche 1 — considered the first operational batch of PWSA sats that would provide regional coverage of the Earth — in September 2024. That date was then postponed and re-slated for spring 2025, largely due to supply chain bottlenecks that have been a persistent hurdle in the architecture’s development.
Tranche 1 will consist of 158 satellites, including 126 in the transport layer, 28 in the tracking layer and four “missile defense demonstration” satellites. Northrop Grumman, Lockheed Martin, York Space Systems and L3Harris are all prime contractors on the program.
The number of sats is a stark contrast to previous military space constellations, which historically only included a small quantity of large and exquisite space vehicles. As a result, both SDA and the space industrial base have been challenged to deliver critical parts — including optical communications terminals (OCT) and encryption devices — on time and at the scale needed to launch the PWSA.
“OCTs have experienced some scaling issues, encryption devices are limited and subject to approval outside SDA, propulsion systems were a challenge on [tranche 1] due to business issues as a supplier that several [tranche 1] prime vendors were using,” an SDA official told DefenseScoop on background.
The launch campaign for tranche 1 will begin with the transport layer, the official added. However, the agency has not yet determined which vendor will be the first to go on orbit in summer 2025, or how many space vehicles will be part of the inaugural tranche 1 launch, they said.
SDA emphasized that despite the latest delay in launching Tranche 1, the agency is committed to finishing on-orbit test and checkout of the satellites by mid-2026 and delivering “the entire initial warfighting capability” in early 2027.
“We are conducting enhanced integration checks and testing on the ground between now and the start of launch which helps build a higher degree of operational confidence,” the SDA official said. “It should also smooth out the test and checkout process on orbit to allow us to get to initial warfighting capabilities in 2027, as the warfighter is expecting.”
The official said subsequent launch campaigns for tranches 2 and 3 are still on track, noting that SDA began the acquisition process for tranche 3 earlier to allow for more time between award and launch. Because the supply chain issues impeding tranche 1 are related to scaling up production, the agency believes it will experience fewer delays once the industrial base catches up to SDA’s demand, they added.
“SDA’s top priority is to quickly deliver capabilities promised to the warfighter. Launch is a major milestone but one in a much larger path to delivering viable capabilities. Our goal remains to rapidly deliver functional capabilities with a high degree of operational confidence,” the agency said in a statement.